More progress is being made on constructing the new Sandy Hook School. Work that's slated to be done this month on the new Sandy Hook School includes completing the roof of Wing A and begin roofing Wing B. Interior masonry walls in Wings C and D are also slated to start going up.
The work is being done in six phases, with actual construction, playgrounds and fixtures and furnishing still on the schedule. Photos of the construction show significant progress on the gymnasium and the roof deck for Wing D.
The building is on target to be open and ready for use for the 2016-2017 school year.