The new Sandy Hook School is on track to open at the start of the next school year.
The contractor building the new Sandy Hook Elementary School says work is progressing at the Newtown site.
Work scheduled to take place this month includes beginning to install the windows, ceilings and soffits at Wing A. Utility installation at Wing B along with closure of the interior walls there is set to get underway. Interior wall framing at Wings C and D will be done. Stone veneer at the front wall of the building will be started. Curbing and road work at Dickinson Drive and Riverside Road will continue this month.