More progress seen at site of new Sandy Hook School

The warm weather has helped move along the building of a new Sandy Hook Elementary School.

 

More progress is being reported on the project, which is scheduled to be completed next year and ready for use by the fall start of the school year.  Painting is being completed in Wing A, windows are being installed on Wing B, weatherproofing is being done on the exterior walls of Wings C and D and some road work is being done on Riverside Road.  Photos from last month at the site show that some bathrooms are being tiled and more drywall is up across the site.  Masonry work also continues. 

 

Abatement and Demolition Phases were completed in 2013. Site Work began last October; and Building began in February.

 

 

(Photos Courtesy: https://www.sandyhook2016.com/)