Mid-January progress reported at the new Sandy Hook School site

Significant progress has been made at the Sandy Hook School construction site.  The first coat of paint has gone up in Wing B of the new school building.  The ceiling was being finished in Wing C and drywall going up in Wing D. 

 

Curbing continues to be installed outside along the bus loop and the concrete walls at the front entry bridges were worked on.  Select trees were also planted and retaining walls completed thanks to a mild start to the winter. 

 

The building is expected to be completed and ready for classes to start this fall.

 

 