Significant progress has been made at the Sandy Hook School construction site.
Thanks to a relatively mild winter, there's been a lot of work done on the new school. Flooring installation has started in Wings B and C, the ceilings are being finished in Wing C and the lobby curtain wall framing is being installed. Concrete site walls continue to be installed, the first coat of paint is going up in Wing C and the bathrooms in Wing B are being finished.
The new Sandy Hook School is expected to be completed and ready for classes this fall.
(Photos SandyHook2016.com: B Wing Corridor)
(Bus Loop)
(D Wing Room)
(Entry Bridge Walls)
(Exterior Sunshades)