Brookfield streetscaping project advances

Eversource Energy has completed moving its wires over new poles in the Four Corners area of Brookfield as the town continues a streetscape project. Charter is scheduled to move its cable off the old poles to the new, followed by Frontier.

 

The granite curbing and new driveway aprons have been installed on the east side of Federal Road from the Shell Gas Station to the northern boundary of Phase 1. Work has started on Station Road, Superior Service and the Mobil Gas Station north to the Agora Restaurant. 

 

Construction has reached the west side of Federal Road, with the project on time and under budget.  Phase I should be completed by the middle of November. 

 

Phase II could start next summer and is fully funded with $865,000 in grant money.  $475,000 in town money has been budgeted for this phase.