New Milford decides against angled parking spaces at Young's Field

Young's Field paving is complete in New Milford.  The parking lot by the Public Works building will be paved next.  The town is waiting on a handicap ramp to complete the work. Parking lines will be taped within the next two weeks. 

 

An assessment was done about angling the parking spots or keeping them straight.  Mayor Pete Bass says if they are angled, New Milford will lose about 20 parking spaces so it was decided to keep the line straight. 

 

There was a delaying in paving Railroad Street due to the weather, but it has been milled and is scheduled to be paved this Monday.

 

Bass has also provided an update on progress at the Still River Roundabout.  The cement and calking have been completed and tested.  The contractor will need about two days for milling and three for paving. The tentative date for this is September 24th. 