Listeners Club

Forgot Password

Not a Member? Sign up here!

banner

Local Headlines

Timeline detailed for Sandy Hook Permanent Memorial

The Sandy Hook Permanent Memorial Commission is not meeting this month.  The group is starting to work on a timeline for getting the former SAC field site opened as the memorial.  First Selectman Dan Rosenthal says once the project is through advanced design, with better cost estimation, there will be public meetings so residents can view what is intended to be built.  The process with the Board of Selectmen, Board of Finance and Legislative Council will happen in July or August in order to get it on the November ballot.  Contractor bids are slated to be due by the end of October.  Construction would take 48 weeks, including winter work.  The permitting process with the state Department of Energy and Environmental Protection and the Army Corps of Engineers can happen after the referendum.  The next Commission meeting will be held January 9th. 

On Air Now

Armstrong & Getty

Local Headlines