Gaylord Road Bridge pre-construction set to start in New Milford

An updated has been given by New Milford officials on Gaylord Road Bridge construction.  The Public Works Department says the recast box sections/walls are currently in fabrication and should be finished by mid-April when work will begin.  Eversource is expected to move the poles in this half of March.  The overhead wires should be relocated around April 11th The contractor will wait for confirmation of the wires being moved before starting the job.  Detour signs will go in this week but will remain covered until work begins.  Completion is expected in mid-August.