Agreement signed for new contractor on New Milford High School roof project

New Milford Mayor Pete Bass has signed an agreement with the former High School roof contractor's bonding agent to allow Greenwood Industries to take over the standing steam roof project.  That was the work that was being done July 5th when a fire broke out.  The cause remains under investigation by the New Milford Fire Marshal's Office.  The insurance company has now turned over the scene to the town.  The agreement with the bonding agent was vetted by Town Attorney Randy DiBella.  Once the permanent roof repair is complete, Greenwood will complete the standing seam roof project.  Belfor the Subcontractor continue the damaged roof repair.  Greenwood is meeting with town and school officials on the logistics and timeframe of the roof project.